ISTQB Foundation Sample Question Paper No. 16
Q. 1: Which of the following combinations correctly
describes a valid approach to
component testing:
i) Functional testing of the component in isolation.
ii) Structure-based testing of the code without recording
incidents.
iii) Automated tests that are run until the
component passes. iv) Functional
testing of the interfaces between modules.
A. i and ii.
B. I, ii and iii
C. iii.
D. ii and iv
Q. 2: Which of the following is a purpose of the
review planning phase?
A. Log defects.
B. Explain the documents
to the participants.
C. Gather metrics.
D. Allocate the individual
roles.
Q. 3: A defect arrival rate curve:
A. Shows the number of
newly discovered defects per unit time
B. Shows the number of
open defects per unit time.
C. Shows the cumulative
total number of defects found up to this time.
D. Any of these, depending
on the company.
Q. 4: Which is the best definition of complete
testing:
A. You have discovered
every bug in the program.
B. You have tested every
statement, branch, and combination of branches in the
program.
C. You have completed
every test in the test plan.
D. You have reached the
scheduled ship date.
Q. 5: Complete statement and branch coverage means:
A. That you have tested
every statement in the program.
B. That you have tested
every statement and every branch in the program.
C. That you have tested
every IF statement in the program.
D. That you have tested
every combination of values of IF statements in the program
Q. 6: There are several risks of managing your
project's schedule with a
statistical reliability model. These include (choose
one or more of the following):
A. Testers spend more
energy early in the product trying to find bugs than preparing to
do the rest of the
project's work more efficiently
B. Managers might not
realize that the testing effort is ineffective, late in the project,
because they expect a low
rate of bug finding, so the low rate achieved doesn't alarm
them.
C. It can increase the
end-of-project pressure on testers to not find bugs, or to not report
bugs.
D. All of the above
Q. 7: Typical defects that are easier to find in
reviews than in dynamic testing are:
A. Deviations from
standards,
B. Requirement defects,
C. Design defects,
D. Insufficient
maintainability and incorrect interface specifications. E. All of the above.
Q. 8: Reviews, static analysis and dynamic testing
have the same objective
A. Identifying defects.
B. Fixing defects.
C. A. and B
D. None of the above
Q. 9: We can achieve complete statement coverage but
still miss bugs because:
A. The failure occurs only
if you reach a statement taking the TRUE branch of an IF
statement, and you got to
the statement with a test that passed through the FALSE
branch.
B. The failure depends on
the program's inability to handle specific data values, rather
than on the program's flow
of control.
C. We are not required to
test code that customers are unlikely to execute.
D. All of the above
Q. 10: Measurement dysfunction is a problem because:
A. Even though the numbers
you look at appear better, to achieve these numbers,
people are doing other
aspects of their work much less well.
B. We don't know how to
measure a variable (our measurement is dysfunctional) and so
we don't know how to
interpret the result.
C. You are measuring the
wrong thing and thus reaching the wrong conclusions.
D. All of the above.
Q. 11: Important consequences of the impossibility
of complete testing are
(Choose one or more answers):
A. We can never be certain
that the program is bug free.
B. We have no definite
stopping point for testing, which makes it easier for some
managers to argue for very
little testing.
C. We have no easy answer
for what testing tasks should always be required, because
every task takes time that
could be spent on other high importance tasks.
D. All of the above.
Q. 12: Poor software characteristics are
A. Only Project risks
B. Only Product risks
C. Project risks and
Product risks
D. Project risks or
Product risks
Q. 13: System testing should investigate
A. Non-functional
requirements only not Functional requirements
B. Functional requirements
only not non-functional requirements
C. Non-functional
requirements and Functional requirements
D. Non-functional
requirements or Functional requirements
Q. 14: Contract and regulation testing is a part of
A. System testing
B. Acceptance testing
C. Integration testing
D. Smoke testing
Q. 15: Find the correct flow of the phases of a
formal review
A. Planning, Review
meeting, Rework, Kick off
B. Planning, Individual
preparation, Kick off, Rework
C. Planning, Review
meeting, Rework, Follow up
D. Planning, Individual
preparation, Follow up, Kick off
Q. 16: Which is not the testing objectives
A. Finding defects
B. Gaining confidence
about the level of quality and providing information
C. Preventing defects.
D. Debugging defects
Q. 17: Maintenance releases and technical assistance
centers are examples of
which of the following costs of quality?
A. External failure
B. Internal failure
C. Appraisal
D. Prevention
Q. 18: Which is not the project risks
A. Supplier issues
B. Organization factors
C. Technical issues
D. Error-prone software
delivered
Q. 19: Bug life cycle
A. Open, Assigned, Fixed,
Closed
B. Open, Fixed, Assigned,
Closed
C. Assigned, Open, Closed,
Fixed
D. Assigned, Open, Fixed,
Closed
Q. 20: Who is responsible for document all the
issues, problems and open point
that were identified during the review meeting
A. Moderator
B. Scribe
C. Reviewers
D. Author
Q. 21: ‘X’ has given a data on a person age, which
should be between 1 to 99.
Using
BVA which is the appropriate one
A. 0,1,2,99
B. 1, 99, 100, 98
C. 0, 1, 99, 100
D. –1, 0, 1, 99
Q. 22: Which is not a testing principle
A. Early testing
B. Defect clustering
C. Pesticide paradox
D. Exhaustive testing
Q. 23: A project that is in the implementation phase
is six weeks behind schedule.
The delivery date for the product is four months
away. The project is not allowed
to slip the delivery date or compromise on the
quality standards established for
his product. Which of the following actions would
bring this project back on
schedule?
A. Eliminate some of the
requirements that have not yet been implemented.
B. Add more engineers to
the project to make up for lost work.
C. Ask the current
developers to work overtime until the lost work is recovered.
D. Hire more software
quality assurance personnel.
Q. 24: The Testing will be performed by the people
at client own locations
A. Alpha testing
B. Field testing
C. Performance testing
D. System testing
Q. 25: Which of the following is the standard for
the Software product quality
A. ISO 1926
B. ISO 829
C. ISO 1012
D. ISO 1028
Q. 26: Which is not a black box testing technique
A. Equivalence partition
B. Decision tables
C. Transaction diagrams
D. Decision testing
Q. 27: Find the mismatch
A. Test data preparation
tools – Manipulate Data bases
B. Test design tools –
Generate test inputs
C. Requirement management
tools – Enables individual tests to be traceable
D. Configuration
management tools – Check for consistence
Q. 28: Use cases can be performed to test
A. Performance testing
B. Unit testing
C. Business scenarios
D. Static testing
Q. 29: Purpose of test design technique is
A. Identifying test
conditions only, not Identifying test cases
B. Not Identifying test
conditions, Identifying test cases only
C. Identifying test
conditions and Identifying test cases
D. Identifying test
conditions or Identifying test cases
Q. 30: One person has been dominating the current
software process
improvement meeting. Which of the following
techniques should the facilitator
use to bring other team members into the discussion?
A. Confront the person and
ask that other team members be allowed to express their
opinions.
B. Wait for the person to
pause, acknowledge the person’ s opinion, and ask for
someone else’ s opinion.
C. Switch the topic to an
issue about which the person does not have a strong opinion.
D. Express an opinion that
differs from the person’ s opinion in order to encourage
others to express their
ideas.
Q. 31: Stochastic testing using statistical
information or operational profiles uses
the following method
A. Heuristic testing
approach
B. Methodical testing
approach
C. Model based testing
approach
D. Process or standard
compliant testing approach
Q. 32: A software model that can’t be used in
functional testing
A. Process flow model
B. State transaction model
C. Menu structure model
D. Plain language
specification model
Q. 33: Arc testing is known as
A. Branch testing
B. Agile testing
C. Beta testing
D. Ad-hoc testing
Q. 34: The purpose of exit criteria is
A. Define when to stop
testing
B. End of test level
C. When a set of tests has
achieved a specific pre condition
D. All of the above
Q. 35: The ____________ technique can be used to
achieve input and output
coverage
A. Boundary value analysis
B. Equivalence partitioning
C. Decision table testing
D. State transition
testing
Q. 36: The ____________ testing is performed at the
developing organization’s
site
A. Unit testing
B. Regression testing
C. Alpha testing
D. Integration testing
Q. 37: What is the main purpose of Informal review
A. Inexpensive way to get
some benefit
B. Find defects
C. Learning, gaining
understanding, effect finding
D. Discuss, make
decisions, solve technical problems
Q. 38: Which is not a Component testing
A. Check the memory leaks
B. Check the robustness
C. Check the branch
coverage
D. Check the decision
tables
Q. 39: The software engineer's role in tool
selection is
A. To identify, evaluate,
and rank tools, and recommend tools to management
B. To determine what kind
of tool is needed, then find it and buy it
C. To initiate the tool
search and present a case to management
D. To identify, evaluate
and select the tools
Q. 40: Which is not the fundamental test process
A. Planning and control
B. Test closure activities
D. None
Answers:
Q.1-B
Q.2-D
Q.3-A
Q.4-A
Q.5-B
Q.6-D
Q.7-E
Q.8-A
Q.9-B
Q.10-A
Q.11-D
Q.12-B
Q.13-C
Q.14-B
Q.15-C
Q.16-D
Q.17-A
Q.18-D
Q.19-A
Q.20-B
Q.21-C
Q.22-D
Q.23-A
Q.24-B
Q.25-A
Q.26-D
Q.27-D
Q.28-C
Q.29-C
Q.30-B
Q.31-C
Q.32-C
Q.33-A
Q.34-D
Q.35-B
Q.36-C
Q.37-A
Q.38-D
Q.39-A
Q.40-D